Branches
Major branches:
Master is the source of all truth
- All branches are off Master
- All work branches spawned directly off (current setup)
- When a branch is ready to be tested, a Draft-PR is made to Master
- When ready for branches to be moved into Production, a Release Candidate (RC) is spawned off Master.
- RC is only merged to Master after release to Production
Moving from “Sprints” to “Cycles (of growth)”
- Tickets are still broken down into “1 week work” chunks
- “Sprint” infers that tickets need to be completed in a set span of time
- Induces a rush to get tickets done
- Pressure to release “good enough” vs “good”
- Adds a bad level of competition between developers (I got this many done this sprint!)
- “Cycle”
- There is still a push to get them loaded onto the “next” release, but much less “do or die”.
- Pushes the iterative mindset
- Picking up the speed of deployments
- Nothing can get “held back” just because one of the tickets needed more work after feedback.
New Git-Flow
- Developers get/choose the tickets to work and spawn their working branch
- Once ready, Draft-PR to Master
- All branch-specific and regression testing is done then.
- Friday
- Release Candidate is spawned from Master
- All working-branches that are ready are merged near end of day.
- Final QA testing is done on the “push” branch. (Should be mostly automated)
- Monday (assuming code has passed all tests)
- RC is demoed to Michael Gao and Crystal.
- If any aren’t given immediate go-ahead, they are pulled from the RC
- By “pulled” it is meant the RC is killed, a new one created, and the approved work branches are merged to the new RC.
- RC is pushed to PreProd for anyone to test and get ready for Push-to-Prod
- Thursday
- Unless there are last minute issues, RC is put on Production.
- Tuesday
- If there were no issues, RC is merged to Master
- If there are issues, it is evaluated if they should be treated as an additional “BugFix” or needing full roll-back.
- If BugFix, RC is merged to Master and new BugFix branch is spawned from Master and moved into the normal cycle.
- If full roll-back is required, Master is Pushed to Prod and the RC abandoned.
- Wednesday
HotFixes are put through a sped-up version of this flow.